Highway 90 Widening Remains on Schedule

The KY 90 widening project in the Zollicoffer area of Wayne County continues to progress.

 

The project was awarded for construction to Hinkle Construction Services LLC on February 26th, in the amount of $7,122,209.34.  Crews have been busy the past few months clearing debris from the right of ways and installing cross drains. Work will continue to move closer to paving as we head into the fall, the contract completion date is June 30th, 2022.